BEECH HILL STUDENT ACCOMMODATION

Project Overview;

Beech Hill is a new boutique student accommodation block in Exeter. Working together with Study Inn and Dako Construction work has started on this new project.  The site includes a gym, games room and steam room and is located on Walnut Gardens opening September 2021.

Services Provided;

Centralised Hot Water Generation
Ventilation to all rooms
Comfort Cooling to Reception & Comms rooms
MVHR Ventilation to communal student areas/Gym
Landlords communal fire alarm system
First & Second fix of all electrical equipment within the Apartment & Communal areas
Wiring & Connection of the mechanical controls to the centralised boiler plant
Door Monitoring System
Access Control System
CCTV
Solar PV panels

Contract Value

Circa £1.35million

Development

New Build Student Accommodation

Client

Dako Construction & Study Inn

Duration

March 2021 – September 2021

CITY ARCADE EXETER

Project Overview;

City Arcade is a new 64 bedroom student accommodation block in Exeter, MEP are undertaking the design and installation of Mechanical & Electrical Services.

Services Provided;

Centralised Hot Water Generation
MEV ventilation to all rooms
Comfort Cooling to Communal Areas
Landlords communal fire alarm system
First & Second fix of all electrical equipment within the Apartment & Communal areas
Wiring & Connection of the mechanical controls to the centralised boiler plant
AOV System
Access Control System
CCTV
Solar PV panels

Contract Value

Circa 560K

Development

New Build Student Accommodation

Client

Urbn Construction

Duration

December 2018 – June 2020

STRONGMANS YARD

Project Overview;

Located on the site of the old Falmouth Coach Works large refurbishment of student housing scheme. The flats are made up of three and four bedrooms as well as single occupancy studios. The accommodation is split over three blocks with a total of 134 bedrooms. The ranges of the accommodation are from two to six storeys in height and this compliments the area that is in a quarry.

Services Provided;

Centralised Hot Water Generation
MEV ventilation to all rooms
Comfort Cooling to Office / Gym
MVHR Ventilation to Gym
Landlords communal fire alarm system
First & Second fix of all electrical equipment within the Apartment & Communal areas
Wiring & Connection of the mechanical controls to the centralised boiler plant
Sprinkler System
Access Control System to block B door
CCTV
Solar PV panels

Contract Value

Circa £1.1 million

Development

Refurb Coach works into student housing

Client

Urbn Construction

Duration

November 2019 – August 2020

OCEAN BOWL

Project Overview;

Ocean Bowl adjacent to Falmouth docks railway station is a 190 bed student complex. The is constructed of 5 blocks including study room, reception. Complete with a gym.

Services Provided;

Centralised Hot Water Generation
MEV ventilation to all rooms
Comfort Cooling to Communal Areas Block D
MVHR Ventilation to communal Gym
Landlords communal fire alarm system
First & Second fix of all electrical equipment within the Apartment & Communal areas
Wiring & Connection of the mechanical controls to the centralised boiler plant
Door Monitoring System
Access Control System
CCTV
Solar PV panels

Contract Value

Circa £1.4million

Development

New Build Student Accommodation

Client

Urbn Construction

Duration

May 2018 – August 2019

YEALMPSTONE SCHOOL

Project Overview;

Despite extremely muddy conditions, building works at Yealmpstone Farm Primary School are now well underway with the substructure in place and ready for the main ground floor slab.

The school pupils are completely segregated from the building works, in order that we can work safely on this occupied site.

The project, which started at the beginning of October 2017, will see the existing primary school being developed with the scope of works including:

Services Provided;

Internal remodelling
New eight classroom extension
Refurbished external play areas

Contract Value

Circa £700k

Development

New Border Control Building

Client

Knights Brown

Duration

July 2021 – October 2022

Tor Bridge and Cann School

Project Overview;

Refurb of toilets/classroom and extension

Services Provided;

Hot and cold water
heating
sprinklers
Sanitaryware

Contract Value

£75k

Development

Extension and refurb of toilet and classroom

Client

Classic Builders

Duration

July 21 – July 22

BAMPFYLDE STREET

Project Overview;

Bampflyde Street is a new 150 bedroom student accommodation block in Exeter, MEP are undertaking the design and installation of Mechanical & Electrical Services.

Services Provided;

Centralised Hot Water Generation
MEV ventilation to all rooms
Comfort Cooling to Communal Areas
MVHR Ventilation to communal student areas
Landlords communal fire alarm system
First & Second fix of all electrical equipment within the Apartment & Communal areas
Wiring & Connection of the mechanical controls to the centralised boiler plant
Door Monitoring System
Access Control System
CCTV
Solar PV panels

Contract Value

Circa £1 million

Development

New Build Student Accommodation

Client

Urbn Construction

Duration

December 2017 – August 2018

CARRICK VIEW FALMOUTH

Project Overview;

Carrick View Falmouth is a brand new student accommodation. All with ensuite shower rooms and cluster kitchen.

Services Provided;

Mechanical & Electrical Installation
AOV Installation
Services Design
Fire Alarm
CCTV
External Lighting
Lighting Protection
Life Safety Systems

Contract Value

Circa £960

Development

New Student Accommodation

Client

Apartments for Falmouth

Duration

June 2020 – Sept 2021

PIER STREET RIVAGE

Project Overview;

Set directly on Plymouth’s striking waterfront and benefiting from breath-taking coastal views, Rivage is understandably one of the region’s most talked about new developments. Only 14 luxurious two and three bedroom apartments are being created, all offering spacious accommodation, sea views and the very best in modern living.

Services Provided;

Centralised boiler plantroom serving heat interface units within the apartments
Underfloor heating
Solar PV panels
MVHR ventilation to apartments
Installation of Sanitary ware
Access Control System-door entry system
Landlords communal fire alarm system
First & second fix of all electrical equipment within the Apartment & Communal areas

Contract Value

£220k

Development

14 Apartments

Client

Rivage Estates

Duration

November 2016 – March 2018

County Hall Toilet Refurb Exeter

Project Overview;

Development Refurb toilet black B Guildhall in Exeter

Services Provided;

Hot & cold water
Sanitaryware
drainage

Contract Value

£95K

Development

Development Refurb toilet block B Guildhall in Exeter

Client

Westcountry Maintenance Services Ltd

Duration

April 2022 – Aug 2022

Winslade Manor, Exeter

Project Overview;

Winslade Manor on the outskirts of Exeter is a beautiful 19th century listed manor house that has been restored into a restaurant/bar/gym and luxury offices.

Services Provided;

Mechanical and Electrical Installation
Door Entry / Intercom System
CCTV System
Fire Alarms
Lightning Protection System
External Lighting
Sanitaryware
Ventilation
Dry Riser

Contract Value

Circa £500k

Development

19th Century Manor House

Client

Urbn Construction

Duration

Nov 19 – March 21

BCP MILLBAY PLYMOUTH

Project Overview;

The Border Control Point building at Millbay in Plymouth is a new building in the heart of Plymouth Docks. Designed to service Plymouth’s new “Free Port” status which will see it become one of eight zones in England that will help create jobs and spark growth in the South West.

Services Provided;

Mechanical & Electrical Installation
Ventilation
Air Conditioning
Fire Alarm
Smoke and Exhaust Ventilation
Life Safety Systems
Lighting Protection
Access Control
Staff panic Alarms

Contract Value

Circa £700k

Development

New Border Control Building

Client

Knights Brown

Duration

July 2021 – October 2022

KARMA ST MARTINS

Project Overview;

Karma St Martins is a luxury island retreat on the Isles of Scilly. Overlooking the sea in a stunning location. It has recently been refurbished and we helped update the current Electrical Installations up to the current regs.

Contract Value

£75K

Development

Refurbishment of Electrical Installations in the luxury Hotel

Client

Karma Group

Duration

April 2023 til March 2024

SMILE DENTAL

Project Overview;

Smile Dental is a conversion of an existing school to new a new up to date Dental Surgery.

Services Provided;

Centralised Hot Water Generation
Heat Recovery Ventilation System
Comfort Cooling to Communal Areas
CCTV
Fire alarm system
First & Second fix of all electrical & mechanical Services
Wiring & Connection of the mechanical controls to the centralised BMS
Access Control System

Contract Value

Circa Half million

Development

Refurb Existing School to Dental Surgery

Client

Brady

Duration

February 2019 – July 2019

THE MERLIN MS CENTRE

Project Overview;

The Merlin Centre is a Cornish Charity and is situated in Mid-Cornwall. It provides therapies for those who are affected and living with Multiple Sclerosis.

Services Provided;

Gas Boiler System
Wet System Underfloor Heating
Services to Pool Equipment
Specialised Ventilation Ductwork to pool area
Hot & Cold Water & above ground drainage
General Lighting & Power
Fire Alarm
Intruder Alarm
Data Installation
Solar PV Panels

Contract Value

Circa £190K

Development

Therapy Centre

Client

Brady Construction

Duration

May 2018 – April 2019

Cambourne Health Centre

Project Overview;

We have been working with CLC Contractors to complete a refurb for the Cambourne Health Centre.

Services Provided;

refit

Contract Value

Circa £160k

Development

Refit

Client

CLC Contractors

Duration

Nov 24 until Feb 2025

CARLYON BAY

Project Overview;

Carlyon Bay (Ocean House) is an over 55’s development of thirty two 2 bed apartments, with access to stunning sea views and beaches. MEP undertook the full design & install of mechanical and electrical services.

Services Provided;

Centralised boiler plant
Heat Interface Units
Underfloor Heating
MVHR Ventilation
Boosted Cold Water
Apartment Hot & Cold Services
Installation of Sanitary ware
Access Control System
Landlords communal fire alarm system
First & second fix of all electrical equipment within the Apartment & Communal areas
Wiring & connection of the mechanical controls to the centralised boiler plant

Contract Value

£830k

Development

32 Apartments

Client

McCarthy & Stone

Duration

November 2016 – August 2017

PEIRSON HOUSE PLYMOUTH

Project Overview;

Peirson House is a contemporary development of 76 Quality Apartments situated in the heart of Plymouth.

MEP Systems undertook the full install of Mechanical and Electrical Services.

Services Provided;

Centralised Boiler Heating System
MEV ventilation to all rooms
Sky & Virgin TV Distribution
Smoke Control System (A.O.V’s.)
Landlords communal fire alarm system
First & Second fix of all electrical & mechanical equipment
Wiring & Connection of the mechanical BMS controls to the centralised boiler plant
Fire Alarm Systems
Access Control & Door Entry System
Sanitary ware
Solar PV panels

Contract Value

Circa £1.7 million

Development

76 Quality Apartments

Client

High Grove/ Moor Manage

Duration

January 2019 – July 2020

PIER STREET RIVAGE

Project Overview;

Set directly on Plymouth’s striking waterfront and benefiting from breath-taking coastal views, Rivage is understandably one of the region’s most talked about new developments. Only 14 luxurious two and three bedroom apartments are being created, all offering spacious accommodation, sea views and the very best in modern living.

The development itself is built in an environmentally friendly manner and even boasts solar panels on its roof. With its breath-taking sea views, chic design, high specification finish, considerable environmental credentials and unrivalled location, there is little doubting the appeal of Rivage.

Services Provided;

Centralised boiler plantroom serving heat interface units within the apartments
Underfloor heating
Solar PV panels
MVHR ventilation to apartments
Installation of Sanitary ware
Access Control System
Landlords communal fire alarm system
First & second fix of all electrical equipment within the Apartment & Communal areas
Car Park Ventilation System

Contract Value

£220k

Development

14 Apartments

Client

Rivage Estates

Duration

November 2016 – March 2018

ST MARGARETS EXETER

Project Overview;

St Margaret’s is a 38 Appartment development within a listed building in Exeter, MEP are undertaking the design and installation of Mechanical & Electrical Services, including district and ground source heating.

Services Provided;

Ground Source Heat Pumps (Via Bore Holes)
Centralised District Heating System including Pre-Insulated pipework
First & Second fix of all Mechanical & Electrical equipment in apartment areas
Communal TV System
Landlords communal fire alarm system
First & Second Fix of all Electrical & Mechanical equipment within the communal areas
Wiring & Connection of the mechanical BMS controls
Lightning Connections
Access Control System
Solar PV Panels
Central MCW Boosted Supplies

Contract Value

Circa £2 million

Development

38 New Apartments in a listed property

Client

Urbn Construction

Duration

December 2019 – June 2021

Coombe Bank Assisted Living

Project Overview;

The block is a sheltered living scheme and consists of 66 self-contained flats. The works involve the complete strip out of the existing heating and water systems throughout the site.

Services Provided;

Centralised plantroom
LTHW
Domestic hot and cold water
Heat interface unit installation
fire alarm
data
communal TV
lighting

Contract Value

Circa £1.1M

Development

Building Refurb

Client

Devon Contractors

Duration

Jan 2022 – March 2023

Duration

Jan 2022 – March 2023

West Carclaze Area B & C

Project Overview;

Carclaze Area D in Cornwall is to install all the M & E Services together with Air Source Heat Pump and Underfloor Heating.

Services Provided;

Mechanical & Electrical Installation
PV Installation
Battery Storage
Electrical Vehicle Chargers
Sound and Air Testing
External Lighting
AOV Installations to Apartment Blocks

Contract Value

£4M

Development

First Phase 169 new build houses

Client

Eco-Bos

Duration

June 2024 – present time

NORTH ROAD PHASE 5

Project Overview;

North Prospect Phase 5 is 143 homes including 46 affordable rent, 31 shared ownership, 66 private sale. MEP Systems works included the M & E Services to 33 new apartments in a 4 storey block.

Services Provided;

Mechanical & Electrical Installation
AOV Installation
Rainwater Installation
Fire Alarm
CCTV
External Lighting
Lighting Protection
Life Safety Systems

Contract Value

Circa £880K

Development

33 New Apartments

Client

Plymouth Community Homes

Duration

Feb 2021 – March 2022

HARBOUR ARCH PLYMOUTH

Project Overview;

Harbour Arch is a stunning new Apartment Block comprising of 14 luxury two and three bedroom apartments and penthouses which will be a lovely new property at Sutton Harbour.

Services Provided;

Mechanical & Electrical Installation
AOV Installation
Rainwater Installation
Fire Alarm
CCTV
External Lighting
Lighting Protection
Life Safety Systems

Contract Value

Circa £570K

Development

New Luxury Apartment Block

Client

Sutton Harbour Group

Duration

November 2021 – June 2022

Padstow Harbour Hotel

Project Overview;

Situated in the grounds of the Padstow Harbour Hotel we are currently building 10 x luxury new apartments. These apartments should have amazing views overlooking the harbour.

Contract Value

£300K

Development

New Luxury Apartment Block

Client

AH Construction

Duration

Jan 2022 – June 2023

Budleigh Salterton

Project Overview;

Budleigh Salterton Evans Field is a new build development on the South Devon Coastline. The luxury family homes development is in a popular area in Budleigh Salterton.

Contract Value

£300K

Development

New Housing Development

Client

Classic Builders

Duration

July 2022 – Ongoing

Rolle Gardens, Exmouth

Project Overview;

MEP are working with Acorn Homes to deliver the mechanical and electrical installation to 9 No. houses and 19 No. apartments with associated landlords and external works at the former ERADE site in Exeter.

Services Provided;

Mechanical and Electrical Installation
Door Entry / Intercom System
CCTV System
Fire Alarms
Lightning Protection System
External Lighting
Sanitaryware
Ventilation
Dry Riser

Contract Value

Circa £650k

Development

28 No. apartments and houses

Client

Acorn Homes

Duration

July 2022 – Ongoing

St Leonards Quarter Phase 1 & 2

Project Overview;

MEP are working with Acorn Homes to deliver the mechanical and electrical installation to 30 No. houses and 46 No. apartments with associated landlords and external works at the former ERADE site in Exeter. This is the first phase of two on the site.

Services Provided;

Mechanical and Electrical Installation
Door Entry / Intercom System
Fire Alarms
Lightning Protection System
External Lighting
Sanitaryware
Ventilation
Dry Riser

Contract Value

Circa £4M

Development

146  Houses/ Flats

Client

Acorn Homes

Duration

July 2022  – April 2027

Fort Bovisand

Project Overview;

MEP are pleased to be working with Construction Management company DNA to deliver the electrical and ventilation installation to 6 No. new build cottages on the Fort Bovisand site near Plymouth. We hope this is the first of many phases of work at a very interesting and historic local site.

Services Provided;

Mains Installation
Lighting and Power
TV Installation
Fire Alarm
Electric Vehicle Chargers
Video Intercoms
Mechanical Services Wiring
MVHR Ventilation System

Contract Value

Circa £200K

Development

6 No. high end sea view cottages

Client

Fort Bovisand Developments Ltd.

Duration

July 2022 – Ongoing

The Reservoir, North Hill

Project Overview;

MEP are working with Pure Projects to deliver the mechanical and electrical installation to 68 No. studio bedrooms and 6 No. cluster bedrooms with associated communal and circulation areas at the former RAOB Social Club site in Plymouth. This is a prime site in Plymouth with direct views onto the Plymouth University Campus and across to Plymouth Sound

Services Provided;

Mechanical and Electrical Installation
Door Entry / Intercom System
Fire Alarms
Lightning Protection System
Solar PV
AOV System
Air Conditioning
Sprinkler Installation
Sanitaryware
Ventilation
Dry Riser

Contract Value

circa £1.0M

Development

74 No. bedroom student accommodation

Client

Pure Projects

Duration

June 2022 – July 2022